India SGL Sesa Goa Iron Pig Expension Project
Project totally 11000ton of industrial structural steelworks, divided into four divisions, coke oven(1900ton), blast furnace(3700ton), sinter plant(3400ton) and raw material handling area(2100ton).
Site:Goa,India
Order Date: May,2010
Completed Date: March,2011
Background: Vedanta Sesa Goa Pig Iron Division is the largest merchant producer of Pig Iron in India with production capacity of 80,000 tons per month. Pig Iron Division (PID) started operating in 1992. It was the first to introduce low phosphorous foundry-grade pig iron in India. The PID has three blast furnaces, making SESA’s PID the largest producer of low phosphorous pig iron in India with an installed capacity of 950000 Tones/Year. The company also commissioned an 800,000 tones’ sintering facility that would enable the PID to partially meet its iron ore requirement with sintered iron ore fines, resulting in significant cost savings and increasing efficiencies.
(Picture Above: Site Overview)
(Picture Above: BF Control Building (2 of 3 slabs completed)
(Picture Above: CWPS Civil Equipment Erection in Progress)
(Picture Above: DD PCM&Cast House In Progress)
(Picture Above: Equipment Erection in Progress-PCM Conveyor)
(Picture Above: Flux & fuel crushing building bldg (2 of 5 slabs completed))
(Picture Above: Iron bin civil & structural strl work in progress)
(Picture Above: Proportioning building structural bldg strl erection in progress)
(Picture Above: Proportioning elect building bldg (2 of 4 slabs in progress))
(Picture Above: Refractory work at HBS 2 & 3 in progress, Platform erection in progress)
(Picture Above: Safety water tower(37 m completed))
(Picture Above: Screening building structure bldg strl erection in progress)
(Picture Above: Sinter building structure bldg strl erection in progress)
(Picture Above: Sinter Elect building bldg (3 of 5 slabs completed))
(Picture Above: Slag pool in progress)
(Picture Above: Strl structure erection in progress (Bag filter & dust catcher))
(Picture Above: Eqpt erection in progress(PCM)
(Picture Above: Strl steel structure erection in progress(Stock house))
(Picture Above: Four pole platform erection in progress)
(Picture Above: Hot metal handling erection in progress)
(Picture Above: Steel Structure Production in Progress)
(Picture Above: Steel Structure Container Loading in Progress)
(Picture Above: Steel Structure Container Loading in Progress)
(Picture Above: Steel_Structure_Welder_Testing_WPS_PQR)